The new waterfront expansion and upgrade efforts continue! This month, Market staff have begun working on the replacement of the elevator and staircase that connects visitors between Pike Place Market and the Alaskan Way waterfront.

Construction on this project will run through May of 2023. Keep reading to learn more about what to expect and how to get around!

How to Get Around During the Closure

Construction on the waterfront elevator is expected to last approximately 8 months, and during this time, all visitors will use our Skybridge elevator to travel between Pike Place Market and the waterfront. Signage is placed along this route to help make wayfinding easy.

The Pike Place Market Parking Garage will remain open during construction and will always have elevators available during garage operating hours.

 

How to get to the Waterfront from Pike Place Market (Main Arcade)

Visitors wanting to visit the waterfront will use our Skybridge and Skybridge elevator to travel between Pike Place Market and the waterfront.

  • Find the Skybridge in the Main Arcade between Pike Street and Pine Street. The Skybridge is to the left of Mick’s Peppourri
  • Go through the double doors to the left of Mick’s Peppourri and across the Skybridge. At the end of the bridge, you will find the Skybridge elevator.
  • Take the elevator to level 1 and follow signs throughout the garage that lead visitors to the Alaskan Way waterfront.

Click through the gallery below to familiarize yourself with the route

 

How to get to the Waterfront from Pike Place Market (Western Avenue)

If you are on Western Avenue in Pike Place Market and would like to get to the waterfront, there are two options you can take.

Option #1: Via the Pike Street Hill Climb

Option #2: Via the Skybridge elevator

  • Find the Skybridge elevator entrance just past KUBODE in the plaza of Providence Heritage House at 1533 Western Avenue. Look for blue signs indicating the elevator entrance.
  • Take the Elevator to Level 2 and follow the blue signs to the waterfront.

Click through the gallery below to familiarize yourself with the route

 

How to get to the Pike Place Market from the Waterfront

Visitors wanting to visit Pike Place Market from the waterfront or our garage will use our Skybridge and Skybridge elevator.

  • Look for the signs outside the entrance to the Pike Place Market Parking Garage on Alaskan Way.
  • Once inside the garage, signs will direct visitors to the Skybridge elevator. This elevator is located in the middle of the garage near Western Avenue and has vibrant, colorful murals in the elevator bank. Via the Skybridge elevator, visitors can access all garage floors and directly to Pike Place Market.
  • Take the elevator to Level M to enter the Market at the SkyBridge.
  • Take it to Level 6 to exit at Western Avenue.

Click through the gallery below to familiarize yourself with the route

Project Details

In September, Market staff began replacing the elevator and staircase connecting visitors between Pike Place Market and the Alaskan Way waterfront. This elevator and staircase is located in the rear corner of our parking garage at 1531 Western Avenue.

The new elevator will travel faster between floors and be able to accommodate more people than the current elevator being replaced. We will also replace the current exterior stairs with a new wider staircase that lands at the new Alaskan Way sidewalk.

It is an exciting progressive step in the ongoing development to move visitors between the Market, our garage, the Seattle Aquarium, and the reimagined waterfront currently under construction.

Construction on this project will run through May of 2023.

Be sure to revisit this page, as we will provide ongoing updates throughout the construction process!

Project Highlights (5)

What is happening?

What is happening?

Pike Place Market is replacing the existing waterfront elevator with a new and improved elevator. The existing stairs are also being replaced with new stairs that land at the new Alaskan Way sidewalk.

When will construction happen?

When will construction happen?

Construction will start at the end of September 2022 and is planned to be completed in May 2023.

Will the garage stay open during construction?

Will the garage stay open during construction?

Yes! People will be able to drive in and out of the Pike Place Market Parking Garage, just as they do today. All foot traffic and ADA accessibility will be directed inside the garage to the interior elevators that connect to all the garage floors and directly to the Market via the Skybridge.

Will the stairs stay open during construction?

Will the stairs stay open during construction?

The stairs will be closed during replacement, but temporary stairs for fire exiting will be installed for safety.

What elevator can I use?

What elevator can I use?

During this construction time, visitors can use the Skybridge elevator to get from Pike Place Market to the waterfront and vice versa. Follow the signage through the garage and Pike Place Market to locate this pathway.

Illustrations of the NEW Elevator & Staircase