RENOVATION NEWS & UPDATES

Final Issue: May 2012


Renovation Success: Three Years of Construction after Years of Planning

When Phase I of the renovation began in the spring of 2009, we anticipated that work would continue for three to four years. Now, in the spring of 2012, the major work is done (with remaining work on the Western Avenue windows to take place in the fall). Since each project resulted in a variety of impacts—ranging from short-term to long-term and minor to major—that affected everyone in the Market, it’s great news that we completed the renovation in three years.

Highlights of Each Phase

Phase I work in the Leland and Fairley Buildings, Hillclimb, and Public Market Parking Garage resulted in an improved entry from Western Avenue; a new elevator serving Western Avenue, DownUnder, and the Main Arcade; a new electrical vault and service upgrades; new plumbing lines; an expanded loading dock; flooring repair; and a new mechanical central plant.

Phase II renovation took place in the Corner Market, Sanitary Market, Triangle Building, and First and Pine Building. This phase included major repairs (plumbing, windows, doors, stairs, fire suppression systems and flooring) in all buildings; major seismic and structural upgrades in the Corner, Sanitary and Triangle Buildings; mechanical and electrical upgrades; and new or upgraded HVAC systems. We added a new elevator in the Corner Market Building and new restrooms in the Sanitary Market Building. This phase of renovation created significant tenant impacts that resulted in temporary tenant relocations, temporary business closures, and apartment residents temporarily relocated.

Phase III of renovation involved the Stewart House, Soames-Dunn, and Economy Buildings. We made major repairs, seismic upgrades, and structural improvements in each building. We replaced the exterior brickwork on the Stewart House; added a new public restroom in the Soames-Dunn; and added a new elevator and HVAC system in the Economy Building.

Project Priorities Were Met: Upgraded Systems and Structures, New Restrooms and Elevators
We long knew that capital maintenance issues were mounting throughout the Market’s infrastructure. In September 2006, we engaged a team of architects and engineers to perform a comprehensive study of the buildings the PDA owns and manages. The team worked closely with many in the Market community to develop a plan for the renovation of the buildings and their systems.

Early in this process, we developed a list of priorities that would guide the development of the design work. These priorities are listed below—and all were successfully accomplished during renovation.

1.  Upgrade the electrical systems as needed to serve all of the Market’s needs now and into the foreseeable future.
2.  Perform code-required structural upgrades and additional sensible and prudent upgrades to improve the safety of the Market’s buildings.
3.  Provide sensible and cost-effective upgrades to mechanical systems to allow for the efficient environmental control of interior spaces.
4.  Provide new accessible public restrooms of reasonable size and located appropriately.
5.  Provide new elevators and other features as required to improve accessibility for disabled people and service to the Market’s buildings.

Thank You, Everyone!
We are thankful for the cooperation of everyone in the Market community. We also want to thank Seattle voters, who made this work possible. In November 2008, a taxpayer-funded property tax levy to update and replace the Market’s aging infrastructure was approved by more than 60% of those who voted in the election.

An Update on Phase III Completed Work

The major renovation work of Phase III is now complete. The Economy Atrium is open with the new elevator serving all floors, including Post Alley. After nearly three years of almost constant construction activity, the Market’s renovation effort is largely complete with the restoration of the windows on Western to be addressed in the fall. All residents and businesses are back in their permanent locations with the exception of Cedar River Group (scheduled to move back in April), Chocolate & Ice Cream Delight (which is pending final approval), and the build-out of the Soames -Dunn retail reconfiguration.

Recent work completed:
Scaffolding around Stewart House and the Economy building has been removed.
Construction of new stairs to the Soames/Dunn basement complete.
New Soames/Dunn restrooms complete and ready to open in April.
Economy Atrium opened, including the new elevator, new seating areas, and access to the South Arcade.
Final seismic work in the Soames-Dunn Building, with roof nailing required by the City underway.
Final water testing of Stewart House windows is now complete.

Read previous editions of Renovation News:

2012: January, February, March, April, May

2011: January, February, March, April, May, June, July, August, September, October, November, December

2010: January, February, March, April, May, June, July, August, September, October, November, December

2009: January, February, March, April, May, June, July, August, September, October, November, December

JOIN THE MAILING LIST

Sign-up to receive news & announcements via email.

Learn More